Subdivision Process

Months

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

Timeline

*What is required for Settlement?

To be able to settle the sales of the new townhouses built we must have three key elements in place. Code of Compliance, Practical Completion Certificate and the title. The process of obtaining a title is complex. The development must meet all conditions of the resource consent and then the title process involves surveyors, lawyers, local council and LINZ. It can often be difficult to get a good idea of the time frame during this process which is why we’ve indicated the last section of the timeline with a dotted line.

Design

RC Submitted

Site Cleared

Fencing

RC Obtained

Civil Works

Main Driveway

Slabs Poured

Framing

Roofing

Air Barriers

Cladding

Interior

Plumbing

Electrical

Wall Linings

Plaster

Kitchen

Bathroom

Landscaping

Code of
Compliance

Practical
Completion

Settlement*

Fitoff

Paint

Scheme Design

Resource Consent Submission

Site Cleared

Perimeter Fencing

Resource Consent Obtained

Civil Works

Main Driveway Poured

Slabs Poured

Framing

Roofing

Air Barriers

Exterior Cladding

Interior Fitout

Plumbing

Electrical

Wall Linings

Plaster & Painting

Kitchen & Bathroom Installation

Electrical & Plumbing Fitoff

Landscaping

Code of Compliance

Practical Completion

Settlement*