22 Fitzherbert Road
All scaffholding down and landscaping program is 80% complete with interior remedials nearing completion.
Wainuiomata, Lower Hutt
Recently completed:
Next stage:
Landscaping program underway
Interior remedial nearing completion
Estimated completion:
June, 2023
All scaffholding down
Exterior decks complete
Matai Park
Zone 1 into landscaping, Zone 2 into cladding & Zone 3 into framing. Foundations 100% complete across the entire site.
Wainuiomata, Lower Hutt
Recently completed:
Next stage:
Blocks E, F, G, H, I, J, P & Q
Landscaping
Blocks K, L, M, N, O, R, S, T
Cladding 30% complete
Blocks A, B, C, D
Framing underway on B, C, D
Estimated completion:
December, 2023
Blocks E, F, G, H, I, J, P & Q
Scaffholding is down
Landscaping 80% done
Blocks K, L, M, N, O, R, S, T
Roofs on
Windows & doors in
R.A.B & cavity system complete
Blocks A, B, C, D
Foundations poured
5 Dyer Street
Civil works & foundations are complete across the site with main focus now on internal right of way.
Epuni, Lower Hutt
Recently completed:
Next stage:
Internal right-of-way 70% complete
Perimeter footpath
Estimated completion:
January, 2024
All foundations poured
Power transformer installed
7 Wainuiomata Road
Exterior cladding work is 70% complete, and the interior work is nearing completion, flooring work is complete, and carpet installation has been finished. Interior remedial work in underway.
Wainuiomata, Lower Hutt
Recently completed:
Next stage:
Cladding nearing completion
Estimated completion:
June, 2023
Flooring work
Exterior block wall complete
16 Molesworth Street
Interior paint is complete for Block B and underway for Block A. Exterior paint underway for Block A&B.
Taita, Lower Hutt
Recently completed:
Next stage:
Kitchen installation
Estimated completion:
August, 2023
Interior paint complete for Block B
Interior paint nearing completion for Block A
Exterior cladding complete
Exterior paint underway
19 Bush Street
Approaching completion of cladding with kitchens in Blocks B & C complete. Exterior painting in
Naenae, Lower Hutt
Recently completed:
Next stage:
Exterior paint
Landscaping
Kitchens, floor coverings
Estimated completion:
September, 2023
Cladding 80% complete
Blocks C, B kitchens installed. Block A underway
Check out the progress on site